Anonymous wrote:Anonymous wrote:Out of curiosity, does anyone know whether the delayed renovation start date (1/2021) is expected to delay its completion? I.e., are kids going to be in Carver Langston for 1.5 school years (1/2021-6/2022) or two (1/2021-1/2023)?
Oh, nevermind, just found the answer to my own question in the letter: the School-Within-Trailers project will "not impact the overall modernization schedule."
Anonymous wrote:Anonymous wrote:Anonymous wrote:DCPS, per their communication with the SWS community, plans to provide buses from the 10th and F NE school site to the Spingarn swing space. Seems relevant to mention that pickup/drop-off could still happen at the SWS building not just at the Spingarn site, though it would involve a short bus ride for the child.
They do this for every school that’s swinging elsewhere. And the pickup and drop off has always been at the ‘home’ school. And yes they run different buses for the ECE kids and their are aides on them.
They did not do this for Maury...