Anonymous wrote:Anonymous wrote:This school is guaranteed to go bust.
No bet. But I'd bet that there's no way it's going to open in September of 2019.
Anonymous wrote:This school is guaranteed to go bust.
Anonymous wrote:Anonymous wrote:Anonymous wrote:Apparently they have now applied for a permit --meaning one was required in the first place.
I looked at DCRA web site for permits for the 2 addresses, not sure what adress they are are using, but I don't see any permits, but I see that the site was nominated as a landmark a few years ago, but it seems to have stalled. If the preservation groups are still looking to fight about the level of protection for this site, don't pay your full tuition just yet.
These are the two addresses, no permits filed.
4000 CONNECTICUT AVE NW
3007 TILDEN ST NW
Also they are zoned residential R-1-B. Not sure if they then have to make a special application to Zoning to put a school in there. If so that will take a few month to get to a hearing.
If they are R-1-B, then yes they will absolutely have to go through a BZA process to get a special exception to put a private school in a residential zone, which could take a year or more. I have gone through the process when working at a school that applied in an R-1-B. Neighbors typically rally against it and it drags on even longer.
However, Intelsat operated there for years and they were a commercial entity - so either they had a special exception or it is not an R-1-B. Or maybe something to do with it being Federal land as mentioned in the Post article that exempts them from zoning. Maybe someone who knows more about zoning laws can clarify
Anonymous wrote:Anonymous wrote:They have been evasive in efforts to meet with the community.
This stop-work gives a needed pause as they have not been abiding by the rules for construction noise past 7pm.
Keep calling illegal construction line for DC. Every time! They do a really good job for enforcing.
Anonymous wrote:They have been evasive in efforts to meet with the community.
This stop-work gives a needed pause as they have not been abiding by the rules for construction noise past 7pm.
Anonymous wrote:Wait, so the school didn't think it needed to apply for ANY construction permits????
Anonymous wrote:This school is guaranteed to go bust.
Anonymous wrote:Anonymous wrote:Apparently they have now applied for a permit --meaning one was required in the first place.
I looked at DCRA web site for permits for the 2 addresses, not sure what adress they are are using, but I don't see any permits, but I see that the site was nominated as a landmark a few years ago, but it seems to have stalled. If the preservation groups are still looking to fight about the level of protection for this site, don't pay your full tuition just yet.
These are the two addresses, no permits filed.
4000 CONNECTICUT AVE NW
3007 TILDEN ST NW
Also they are zoned residential R-1-B. Not sure if they then have to make a special application to Zoning to put a school in there. If so that will take a few month to get to a hearing.
Anonymous wrote:Apparently they have now applied for a permit --meaning one was required in the first place.