Anonymous wrote:Anonymous wrote:Anonymous wrote:Anonymous wrote:2018 at the earliest, if ever.
What? 2018 approved or concluded?
The question asked when the project would be approved. Given that there are now two-year leases on the site, 2016 + 2 = 2018. That would be the earliest the project would receive approval and GDS could break ground.
Ok, thanks!
Anonymous wrote:Anonymous wrote:Anonymous wrote:2018 at the earliest, if ever.
What? 2018 approved or concluded?
The question asked when the project would be approved. Given that there are now two-year leases on the site, 2016 + 2 = 2018. That would be the earliest the project would receive approval and GDS could break ground.
Anonymous wrote:No PUD, no new campus.
Not sure what math or finance you are considering.
Anonymous wrote:Anonymous wrote:Anonymous wrote:2018 at the earliest, if ever.
What? 2018 approved or concluded?
The question asked when the project would be approved. Given that there are now two-year leases on the site, 2016 + 2 = 2018. That would be the earliest the project would receive approval and GDS could break ground.
Anonymous wrote:Anonymous wrote:Anonymous wrote:Anonymous wrote:Anonymous wrote:2018 at the earliest, if ever.
What? 2018 approved or concluded?
The question asked when the project would be approved. Given that there are now two-year leases on the site, 2016 + 2 = 2018. That would be the earliest the project would receive approval and GDS could break ground.
My understanding is that the want to complete the school/Safeway portion before breaking ground on the retail.
And this would be paid for with what dollars without the PUD?
Anonymous wrote:Anonymous wrote:Anonymous wrote:Anonymous wrote:2018 at the earliest, if ever.
What? 2018 approved or concluded?
The question asked when the project would be approved. Given that there are now two-year leases on the site, 2016 + 2 = 2018. That would be the earliest the project would receive approval and GDS could break ground.
My understanding is that the want to complete the school/Safeway portion before breaking ground on the retail.
Anonymous wrote:Anonymous wrote:Anonymous wrote:Anonymous wrote:2018 at the earliest, if ever.
What? 2018 approved or concluded?
The question asked when the project would be approved. Given that there are now two-year leases on the site, 2016 + 2 = 2018. That would be the earliest the project would receive approval and GDS could break ground.
My understanding is that the want to complete the school/Safeway portion before breaking ground on the retail.
Anonymous wrote:Anonymous wrote:Anonymous wrote:2018 at the earliest, if ever.
What? 2018 approved or concluded?
The question asked when the project would be approved. Given that there are now two-year leases on the site, 2016 + 2 = 2018. That would be the earliest the project would receive approval and GDS could break ground.
Anonymous wrote:Anonymous wrote:2018 at the earliest, if ever.
What? 2018 approved or concluded?
Anonymous wrote:JBG is/was? GDS's crony developer for the Wisconsin Ave site. Their Marriott Wardman project has been in the pipeline for 10+ years.
Anonymous wrote:2018 at the earliest, if ever.