Anonymous wrote:
Anonymous wrote:Plus a new "programmed" ES for BCC/WJ clusters, opening date TBD.
What do you/they mean by “programmed”?
CIP terminology:
“Approved”— Project has an FY 2019 or FY 2020 appropriation for planning
or construction funds approved in the Amended FY 2019–2024 CIP.
“Programmed”—Project has expenditures programmed in a future year of the
CIP for planning and/or construction funds.
“Proposed”—Project has facility planning funds approved for a feasibility study.
“Recommended”—Project has an FY 2021 appropriation recommended for
planning or construction in the FY 2021–2026 CIP.