Anonymous wrote:Recently complete a major project that included both, a really really bad GC and a fantastic GC. Narrowed down to two contractors with nearly the same bids. Unfortunately, selected the local contractor over a contractor that was going to travel 2 hours each day. That contractor, Optimum Construction run by Omar Elrahimy (See the thread - Warning for those looking for a contractor) immediately started trying to get additional funds, did not complete anything and claimed he could not work because of covid unless I would pay 50% more. Needless to say I said no. Went back to the other contractor. They took over the project honoring their original proposal and the only additional costs were for changes where I asked for more. No issues, fantastic to work with. Your GC should be able to do a proposal and stick to it. If not, they failed the first task of being a GC unless they are like Omar Elrahimy.
Anonymous wrote:Anonymous wrote:We had our 3100 sqft basement finished during COVID. We went with a design build firm that quoted us in writing a not to exceed price of $100k. The allowances given to us were for mid/upper grade finishes. We came in $16k once our selections were completed.
They mention all this on their website and not to mention all the work is backed by a 12 month and 24 month punch-out list.
You lost me at 3100 sq foot basement.
Anonymous wrote:Recently complete a major project that included both, a really really bad GC and a fantastic GC. Narrowed down to two contractors with nearly the same bids. Unfortunately, selected the local contractor over a contractor that was going to travel 2 hours each day. That contractor, Optimum Construction run by Omar Elrahimy (See the thread - Warning for those looking for a contractor) immediately started trying to get additional funds, did not complete anything and claimed he could not work because of covid unless I would pay 50% more. Needless to say I said no. Went back to the other contractor. They took over the project honoring their original proposal and the only additional costs were for changes where I asked for more. No issues, fantastic to work with. Your GC should be able to do a proposal and stick to it. If not, they failed the first task of being a GC unless they are like Omar Elrahimy.
Anonymous wrote:Anonymous wrote:Your contract is cost-plus? I think I know why it's going over....
Most high end builders are cost plus. It is a very transparent way of building, if both parties follow contract.
Anonymous wrote:Anonymous wrote:I got an estimate in December 2021 for kitchen remodel. $50k (10 x 10 kitchen, not too luxurious.)
In April 2022 the estimate was revised to well over 70K. I brought it down to 60 by eliminating pendant lights over the sink, a couple of glass-front cabinets, and switching from solid hardwood floor to engineered wood (thin layer of hardwood on top of cheap core.)
Work started July 2022 and ended September 2022. Ended up costing $70k even after my cuts.
This is very silly, PP. I don't know what you were getting done at $70K for 10x10 medium grade kitchen. Your GC took you to the cleaners.
Anonymous wrote:I got an estimate in December 2021 for kitchen remodel. $50k (10 x 10 kitchen, not too luxurious.)
In April 2022 the estimate was revised to well over 70K. I brought it down to 60 by eliminating pendant lights over the sink, a couple of glass-front cabinets, and switching from solid hardwood floor to engineered wood (thin layer of hardwood on top of cheap core.)
Work started July 2022 and ended September 2022. Ended up costing $70k even after my cuts.
Anonymous wrote:Sorry this is happening, it can be really distressing. We did a big renovation, including an addition, and I don’t remember the exact numbers, but we did blow past our original budget. In our case, the contractor was up front about where costs were coming from when we asked about it. It all checked out but was still stressful to write those checks.
I think it’s pretty normal for costs to exceed estimates, especially in this era of inflation/supply chain issues, but definitely don’t be afraid to ask them to justify it.
Anonymous wrote:I got an estimate in December 2021 for kitchen remodel. $50k (10 x 10 kitchen, not too luxurious.)
In April 2022 the estimate was revised to well over 70K. I brought it down to 60 by eliminating pendant lights over the sink, a couple of glass-front cabinets, and switching from solid hardwood floor to engineered wood (thin layer of hardwood on top of cheap core.)
Work started July 2022 and ended September 2022. Ended up costing $70k even after my cuts.
Anonymous wrote:One reason this happening more is that owners don't want to pay for CDs and only contracts the architect for the bare minimum. Then the little details that are required to keep project moving aren't detailed on the drawings. Then there is the cost of figuring out, back tracking, delays. Do that 10-20 times on a house and it adds up fast.
Anonymous wrote:Your contract is cost-plus? I think I know why it's going over....