Anonymous wrote:Does it matter how much lead time we have. Our goal is to order everything we need to order months before we need them to allow for delivery delays and get permits in place early. It sounds like three months is unrealistic, but it just doesn't seem like this should take 5 months.
Who is going to put out the cash to pay for those items to sit? Most builders get their stuff a few days before if not the same day they are going to use it. Permits are a seperate deal than the building part. alos builders don't like material sitting around they tend to grow legs and disappear.
It sounds like you muight be trying to micro manage the job a bit too much, let the builder do their work and appeciate it at the end.