Anonymous
Post 12/08/2022 17:38     Subject: Re:Remodel payment schedule

Not sure where you are located - but in Maryland I have often found:

1/3 upon hiring/contract sign (legally not allowed to be more % than this)

1/3 materials delivered/partial completion

1/3 completion
Anonymous
Post 12/02/2022 20:11     Subject: Remodel payment schedule

<5% is typical.
Anonymous
Post 12/02/2022 20:10     Subject: Re:Remodel payment schedule

Mine is 10%. When I was calling references, one lady said her bank made them adjust it to 30% and that is the only reason she thought they finished. We are wrapping up the project within the next 2 months, so ask me then.

My advice is to spell out what needs to be done at each milestone. It will say "framing" : OK, what exactly does that mean?

Also ask to see receipts or confirmation for all big items that you pay up front like cabinets. We had an issue where things were not ordered, and it set us back months.
Anonymous
Post 12/02/2022 19:18     Subject: Remodel payment schedule

Anonymous wrote:Its typically 10 percent retainage until punch list is completed.


No - it’s not.

Where I work it would not even be legal.
Anonymous
Post 12/01/2022 22:35     Subject: Remodel payment schedule

Its typically 10 percent retainage until punch list is completed.
Anonymous
Post 12/01/2022 06:59     Subject: Remodel payment schedule

Ours was 20% of labor. We paid for the finish materials ourselves but contractor bought drywall etc. this was for kitchen and bathroom remodels.
Anonymous
Post 12/01/2022 05:53     Subject: Remodel payment schedule

Ours was 20% of labor costs (large material costs were paid separately and often directly to the vendor.)
Anonymous
Post 12/01/2022 04:56     Subject: Re:Remodel payment schedule

10-30%. My last bathroom remodel it was 1/3. Make sure to have the draw schedule tied to significant milestones, we learned that lesson the hard way.
Anonymous
Post 11/30/2022 14:47     Subject: Remodel payment schedule

My experience is it's about 10-15%.
Anonymous
Post 11/30/2022 09:30     Subject: Remodel payment schedule

That last payment should be a large enough percentage to incentivise the contractor to complete the job, with the final punch list complete and to your "reasonable" satisfaction.
Anonymous
Post 11/30/2022 08:11     Subject: Remodel payment schedule

Ours is closer to 10%
Anonymous
Post 11/30/2022 00:48     Subject: Re:Remodel payment schedule

Anonymous wrote:Normal. For us, last payment was like 2% and the other 8 or 9 draws plus a deposit were all about even.


Same but now here we are with only the final unpaid and so much work left. I wish we had more money on the line still for leverage.
Anonymous
Post 11/29/2022 23:06     Subject: Re:Remodel payment schedule

Normal. For us, last payment was like 2% and the other 8 or 9 draws plus a deposit were all about even.
Anonymous
Post 11/29/2022 20:42     Subject: Remodel payment schedule

The final payment was very low (a couple thousand), and others were huge, but based on paying for materials, cabinets for example (large kitchen + 3 bathrooms). We were not able to negotiate, as the draws were (mostly) based on their costs for ordering (plus lots of mark up I'm sure)
Anonymous
Post 11/29/2022 18:55     Subject: Remodel payment schedule

If you've done some type of remodel, what % was the final payment? We are beginning a project and talking to contractors. Trying to get a sense of how payments should be scheduled. Also, if the set final amount is a very low percentage, can you negotiate?