Anonymous wrote:We are looking at a house that needs 2.5 bathrooms redone. No plumbing would have to be moved, but all tile and fixtures replaced. If you have done a project like this, what was your timeline from the start of finding contractors till the finish of work. How much did you spend all in? Thank you!
Estimate will vary widely. You didn't tell us how big your bathrooms are and there is a huge price range in cabinets, tiles, fixtures, etc. Demo is expensive if you have mud set tiles that need to come out. If you are in the DC area, even a tiny bathroom is going to be ~$10,000 right now. I would plan on 4ish weeks if you can get all the supplies when you need them.